Decoration schedule saves time and effort

2022-07-22
  • Detail

Before the decoration construction, the owner should ask the foreman in charge of the decoration to show you a schedule for the construction period of the decoration construction, which is not only a plan for the whole decoration process, but also a commitment to the owner. If the construction period is delayed in the future, the owner can safeguard his legitimate rights and interests according to this schedule. In addition, the schedule can also be used as a time reference for the owner to regularly check and accept the project

it is understood that it takes about 45 days from the beginning to the completion to decorate a three bedroom house of 130 square meters. The two bedroom apartment with smaller area can save four or five days, while the duplex apartment with more than 200 square meters needs four or five more days. The process of house decoration can be divided into three stages: early stage, middle stage and late stage

◆ approximate schedule

1. At least 10 days before construction: make design and plan; Select the decoration company and put forward the decoration contents and requirements; Measure relevant data on site and draw detailed drawings; Fully communicate with the designer to determine the final plan

2. At least 5 days before commencement: sign the contract according to the budget; Determine the materials to be used; Make a preliminary budget for the home decoration expenses and compare it with the budget of the home decoration company; Sign the decoration contract

3. At least 2 days before commencement: make preparations before mobilization; Contact the property department and complete the necessary procedures; Say hello to your neighbors; Mobilization of door and window materials and auxiliary materials; Hand over the key of the construction party; Pay the first installment of decoration

4. 1-2 days after commencement: knock on the wall to reform the structure

5. 5-10 days after commencement: install water pipes and circuits; Handling and acceptance of pipeline materials; Acceptance of concealed works

6. 10-20 days after commencement: pave tiles and make walls; Acceptance of mud tile works; Check and accept wall materials, such as wall paint, ceramic tiles, etc

7. 20-30 days after commencement: carpentry and painting; Mobilization acceptance of paint materials; Woodworking project acceptance

8. Start work for 30-50 days: lay the floor and make kitchen and bathroom equipment; Acceptance of floor materials; Cabinet installation acceptance on site; Site installation and acceptance of sanitary products; Buy back electrical appliances and install them; Sanitary products are installed and accepted on site

9. 50-60 days after commencement: conduct acceptance and final accounts; Carry out summary calculation